EA-03-007 · NOV · Issued 2003-03-04 · Reactor Licensees
Action
EA Number
EA-03-007
Licensee
NOV (White)
Category
Reactor Licensees
Action type
NOV
Date issued
2003-03-04
Description
On March 4, 2003, a Notice of Violation was issued for a violation associated with a White SDP finding involving the failure of the high pressure core spray system to start during routine surveillance testing. The violation cited the licensee's failure to implement procedures during the installation and inspection of the high pressure core spray pump breaker from 1994 through October 23, 2002.